The Consent Window: Programming a UK Office Fit-Out Before Day One
Photo: British Cartoon Prints Collection, Public domain, via Wikimedia Commons
There is a particular kind of disappointment reserved for the first Monday of a new lease, when the keys arrive, the contractor arrives, and the landlord's surveyor explains that the licence to alter has not yet been issued. The rent has started. The team is working from a kitchen table. The programme is already behind.
Fit-out delay is rarely caused by one dramatic failure. It is caused by a sequence of ordinary steps — drawings, approvals, fees, insurance certificates, contractor availability — each of which takes longer than the person who has never done it expects. The purpose of this article is to set out a realistic sequence for a 2026 office move, and to show where the pre-signature period can buy time.
Day one is rarely day one
A lease can start on a date when the tenant has no practical ability to occupy. Rent commencement, access for works and the right to trade are three different things, and only the first is guaranteed by the signature. Before committing, establish when access for fit-out will be granted, what landlord approvals are needed to start, and whether early access can be agreed separately from the lease.
What the licence actually authorises
Most leases prohibit alterations without the landlord's consent, and the licence to alter is the document that grants it. Some leases carve out minor works — painting, carpet, non-structural partitions below a certain height — but the carve-outs are narrower than tenants assume. The licence will set out the works approved, the conditions attached, the landlord's fees, and the reinstatement obligation at the end. It may also require a deed of licence, which needs to be completed before work starts.
The information pack the landlord will request
Expect a request for dimensioned drawings, a specification, mechanical and electrical details, and a method statement. The landlord's surveyor will want contractor details, public liability and professional indemnity insurance, a construction phase plan where the Construction (Design and Management) Regulations apply, and a programme. Listed buildings and conservation areas add consent from the local authority. Party wall issues arise more often in office refurbishments than tenants expect, particularly where floor loadings or shared walls are affected.
The pack is not bureaucracy for its own sake: it is the evidence the landlord needs to satisfy itself that the building, its insurers and its other occupiers are protected. A complete pack submitted early moves faster than a partial one submitted twice.
The clock: a realistic sequence
A small fit-out typically needs eight to twelve weeks from first instruction of the designer to a licence being issued, and that assumes a cooperative landlord and a straightforward scheme. The stages overlap, but none disappears.
Allow one to two weeks for measured surveys and concept drawings, two to four weeks for the licence application to be assessed, and a similar period for building regulations approval, which can run in parallel. Tendering to contractors takes three to five weeks, and mobilisation a further two. Add the lead times for bespoke joinery, furniture and IT, which in 2026 remain the most common cause of a slipped practical completion.
A cautious tenant therefore works back from the desired occupation date by sixteen weeks, not eight. Where the works are extensive or the building is listed, twenty weeks is not pessimistic.
Building regulations and the Building Safety Act
The building regulations application is separate from the licence and is not the landlord's responsibility to obtain on the tenant's behalf. Fire safety, means of escape, ventilation, accessibility and energy performance all fall to be demonstrated. The Building Safety Act 2022 has sharpened the focus on competence and on the information handed over at completion, particularly in higher-risk buildings. A contractor who has not worked under the current regime may underestimate the paperwork.
Fees, conditions and the small print
The landlord will usually recover its legal and surveying costs, and may charge a separate licence fee. These sums vary widely — a few hundred pounds for a simple consent, several thousand for a complex one — and they are payable whether or not the works proceed. Conditions commonly include restrictions on working hours, noise, deliveries and contractor parking, a requirement to use the landlord's nominated contractors for certain works, and a reinstatement obligation that should be priced before signature rather than discovered at exit.
Where the programme meets the money
The rent-free period is the tenant's working capital for the fit-out, and every week lost to consent consumes it. Two drafting points are worth pursuing. First, ask for access to the premises before rent commencement for survey, design and, if possible, works. Second, seek a lease clause requiring the landlord to respond to a licence application within a stated period, or at least to confirm receipt and identify missing information promptly. An express long-stop date is rare, but a clear timetable is not.
A pre-signature timetable
Sixteen weeks out: appoint a designer and confirm the brief. Fourteen weeks: heads of terms agreed, and the fit-out requirement reflected in the lease negotiations. Twelve weeks: licence application submitted with the full pack. Ten weeks: building regulations application lodged and tender issued. Eight weeks: tenders returned, contractor appointed subject to consent. Six weeks: licence expected; legal completion of the licence. Four weeks: insurances and construction phase plan in place. Two weeks: mobilisation. Week zero: possession and start on site.
That programme leaves no float. On a real project, float is what stands between a smooth move and a team working from a kitchen table. Build it in before the lease is signed, not after.